1. Chemususu Dam Water Supply Project
The project is at about 71% completion status. The civil works for the treatment work and gravity main to the main reservoir of capacity 5000m3 at Baringo high school is completed.
Eldama Ravine town reticulation system is completed and was commissioned on 7th July, 2019. In addition to the Baringo hill tank, a 750m3 tank at the District Commissioner office compound (DC tank) and 11 No. tanks across the project area are completed while the construction of the other 15 No. tanks is in various stages of completion. The other major distribution mains are on-going.
The source of the water is Chemususu Dam developed in phase I by National Water Conservation and Pipeline Corporation with a capacity of 11million cubic metres. The dam is located in Koibatek Sub County in Baringo County.
The project targets water supply to Eldama Ravine town and its environs, Mogotio Town and its environs, Kabarak University, Kiamunyi area of Nakuru Town and parts of Rongai sub-counties.
2. Kirandich Dam Phase II Water Supply Project
The contract commenced on 6th February 2017 and was supposed to end on 8th December 2018. There were delays in contractor mobilisation to site on time which necessitating contract duration rescheduling through an addendum. The addendum has been negotiated by parties and approved by the Italian Cooperation who is the financier of the project. The contract is, therefore, going to be rescheduled to be effective from 8th December 2018 to 6th December 2020. The project is currently at 12.5% completion.
COMPLETED PROJECTS (2020 to Date) |
||||
No. |
Project |
Scope of Works |
Sub-county |
Beneficiaries |
1 |
Civil works for reinstatement of Kabulyot water project |
Rehabilitation of the existing pipeline network |
Baringo |
3000 |
2 |
Civil works for oldebes water project |
Tank construction and Conveyance system |
Baringo |
1500 |
3 |
Construction works for Soibei community water project |
|
Baringo |
300 |
4 |
Completion of Tugumoi-Tinonei and Chepnyogoson water project |
|
Baringo |
570 |
5 |
Kimotony water pan |
Excavation and Earthworks. |
Baringo |
2000 |
6 |
Mochongoi water project |
Construction of intake works, Gravity main, rising main, 50m3 and 100m3 masonry tanks, pump house, solarisation, and Fencing |
Baringo South |
3000 |
7 |
Solarization of Ndabibi borehole |
Solar Equipping |
Mogotio |
2000 |
8 |
Solar equipping of olkokwe community borehole |
Solarization of borehole |
Mogotio |
700 |
9 |
Tuiseru borehole |
Drilling and test pumping.installation of pumping system and solar equipment. Construction of water kiosk with 10m3 plastic tank. Constructiojn of cattle trough. Pipework and fitting. Fencing and gate |
Mogotio |
600 |
10 |
Boito Secondary School Borehole |
Drilling Equipping and |
Eldama ravine |
2500 |
11 |
Nato Community Borehole Wp |
Drilling Equipping and Civil Works |
Mogotio |
2000 |
12 |
Kabartonjo Referral hospital |
Drilling, Equipping and Civil works |
Baringo North |
50 Outpatients per day and 24 bed capacity Inpatients |
13 |
Civil works for Lokoiwo water project |
Pipe works |
Baringo North |
1500 |
14 |
Orinie Primary School Borehole Water Project |
Equipping and Civil Works |
Eldama Ravine |
1000 |
15 |
Equipping and civil works for Solian girls secondary school borehole |
Equipping and Civil Works |
Eldama Ravine |
1200 |
16 |
Equipping and civil works for Tandui community borehole |
Equipping and Civil works |
Baringo Central |
2000 |
17 |
Tolmo water project |
Construction of 100m3 masonry tank and distribution pipeline |
Eldama Ravine |
1200 |
18 |
Tinosiek borehole |
|
Mogotio |
400 |
19 |
Asenwe Communitty Borehole Wp |
|
Mogotio |
1200 |
20 |
Lemelok Community Borehole Wp |
|
Baringo South |
1600 |
21 |
Kupotwin Community Borehole Wp |
|
Tiaty |
500 |
22 |
Kaiso Community Borehole Wp |
|
Baringo Central |
2500 |
22 |
Kabergei Community Borehole Wp |
|
Mogotio |
450 |
23 |
Marram (Kacheptuyo) |
|
Tiaty |
400 |
24 |
Tenges Community Borehole Wp |
|
Baringo Central |
3000 |
25 |
Tabagon Community Borehole Wp |
|
Baringo Central |
1480 |
26 |
Rimo Community Borehole Wp |
|
Baringo North |
800 |
27 |
Sesoche Community Borehole Wp |
|
Mogotio |
1300 |
28 |
Kabarbaya Community Borehole Wp |
|
Mogotio |
750 |
29 |
Kapyemit Community Borehole Wp |
|
Mogotio |
500 |
30 |
Mosuro Community Borehole Wp |
|
Baringo South |
400 |
31 |
Mogotio Sub-county hospital |
|
Mogotio |
70 Outpatients per day and 150 bed capacity Inpatients |
32 |
Kipkaech(Ngetmoi) dispensary |
|
Baringo Central |
50 Outpatients per day |
33 |
Kotulpogh Bh |
|
Tiaty |
300 |
34 |
Kiplombe Secondary school borehole |
|
Eldama Ravine |
600 |
35 |
Maji Nyekundu Borehole |
|
Mogotio |
2000 |
36 |
KapKiamo Primary School Borehole |
|
Baringo North |
1800 |
37 |
Lelgel Primary School Borehole |
|
Eldama Ravine |
2500 |
38 |
Makoi water project |
|
Mogotio |
3000 |
39 |
Lolmolo-Kokorwonin |
|
Eldama Ravine |
1000 |
ONGOING PROJECTS |
|||||
No. |
Project |
Scope of Works |
Sub county
|
Beneficiaries |
Status |
1. |
Kaptiriony Secondary School Borehole |
Drilling, Test Pumping, Equipping & Civil Works |
Baringo Central |
530 |
Ongoing |
2. |
Kaptir Community BorholeWp |
Drilling Equipping and Civil Works |
Baringo North |
350 |
Ongoing |
3. |
Kapsiloi Community Borehole Wp
|
Drilling Equipping and Civil Works |
Mogotio |
600 |
ongoing |
4. |
Kaptumo phase III Water supply |
Solarization of 2no boreholes. Drilling equipping and civil water for 1No borehole Construction of 100m3 masonry tank. Pipeline installation |
Baringo Central |
3000 |
ongoing |
5. |
Kaboro phase III water supply |
Desilting and fencing of intake Construction of pump house and equipping of booster pump station. Construction of 30m3 masonry tank. |
Baringo North |
2600 |
Ongoing |